Here are
the Answers to the Questions (1-51) in Previous Blog (for Site Supervisors and
Site Engineers):
1. Types
of Cement
1. Ordinary
Portland Cement (OPC) : This is the most widely used type of Cement,
which is suitable for most general concrete constructions. OPC is available in
3 grades. 33,43 & 53 Grade. The Grade represents the strength of cement at
28 days - Eg: For 33 Grade- 33N/mm2
2. Porland
Pozzalano Cement (PPC) : PPC is manufactured by mixing 30% of
Pozzalano to ordinary Portland Cement clinkers. This is used in marine
structures, sewage works (Dams and weirs).
3.Rapid
Hardening Cement
4.Quick
setting Cement
5. White
Cement
6. Rapid
Hardening Cement
7.
Coloured Cement
8. Low
heat Cement
9.
Sulfates resisting Cement
10.
Blast Furnace Slag Cement
11.High
Alumina Cement
12.
Air-entraining Cement
13.
Hydro phobic Cement
14.
Expansive Cement
2. Why
do we use Steel Reinforcement in Concrete?
Concrete
is only strong against forces of compression and has low tensile strength and
ductility. The steel provides tensile strength and extra shear strength. Steel
bonds well with concrete and expands and contracts due to temperature at
similar rates.
3.Unit
weight of Concrete
As per
IS 456-200, unit weight of PCC is 24KN/m3 and RCC is 25KN/m3
4.Unit
weight of Steel
The unit
weight of Steel is 78.5KN/m3
5. What
is M25 Concrete?
As per
IS 456-2000, M- refers Mix and 25- refers Characteristic compressive strength
of concrete (Concrete cube of 150mm x 150mm x150mm tested at the end of 28 days
after casting should be minimum 25 KN/Sq.mm
6.
Different ratios of Grades of Concrete
M5 -
1:5:10
M7.5 -
1:4:8
M10 -
1:3:6
M15 -
1:2:4
M20 -
1:1.5:3
M25 -
1:1:2
M30,
M35, M40 - Design mix followed.
7.Bearing
Capacity of Soil
Bearing
Capacity of the soil is the capacity to support the loads applied to the ground
by foundation of the structure.
8.Minimum
Curing Period
Is
456-2000 recommends that curing duration of concrete must be atleast 7 days,
atleast 10 days for concrete with mineral admixtures. It also recommends that
the curing duration should not be less than 10 days for concrete of OPC exposed
to dry and hot weather conditions and 14 days for concrete with mineral
admixtures in hot and dry weather.
9.
Bending Moment (B.M) & Shear Force (S.F)
A
bending moment is the reaction induced in a structural element when an external
force or moment is applied to the element causing the element to bend. The most
common or simplest structural element subjected to bending moments is the beam.
Shear
force is the force in the beam acting perpendiculat to its longitudinal (x)
axis. For design purposes, the beams ability to resist shear force is more
important than ita ability to resist an axial force. Axial force is the force
in the beam acting parellel to tha longitudinal axis.
10. How
to find out wt of steel bar used for reinforcement
Weight
of bar in Kg/m should be calculated as D2 /
162. D -
Diameter of rod in mm.
11. Two
storeyed buildings
The
building which has two floors is called two storeyed building
12. What
is the standard height of each floor?
The
standard height of each floor should be 3m.
13.Standard
slope for staircases
As per
IS 456, the slope or pitch of stair should be between 25 degrees to 40 degrees.
(the preferred slope will be 30-35 degrees usually).
14.
Standard height of Rise and width of Tread in Staircase
Rise -
150 -200 mm; Tread - 250-300 mm
15.Crank
length in Slab
The
Crank length of bars in slab is 0.42D. D= Depth of slab-Top cover-Bottom
Cover.
16.Moment
of Inertia
The
moment of Inertia is a geometrical property of a beam and depends on a
reference axis. The Area of Moment of Inertia of a beam's cross sectional area
measures the beam's ability to resist bending.The larger the Moment of Inertia,
the less beam will bend.
17 Types
of Slump
a) True
Slump: The concrete mass after the test - when slumps evenly all
around without disintegration is called the true slump.
b) Shear Slump: When one-half of the concrete mass
slide down the other is called the shear slump. This type of slump obtained in
a lean concrete mix.
c) Collapse
slump: When the sample is collapsed due to excessive water, it is
known as collapse slump.
d) Zero
Slump: For very stiff and dry mixes, it does not show any changes of the
slump after removing the slump cone.
18.
Retaining wall
A wall
constructed to resist the pressure of an earth filling is known as Retaining
wall.
19.One-way
/ Two-way slabs
One-way
slab: Ratio of Longer span / Shorter span >2
Two-way
slab: Ratio of Longer span / Shorter span < / = 2
20.
Recommended slumps
As per
IS 456, Mass concrete, Lightly reinforced walls, slabs, beams, columns, canal
lining, strip footing - 25 -75 mm
Heavily
Reinforced slabs, beams, columns - 50-100 mm
21.
Checking Levels at site
Levels
can be checked with Sprit level, Dumpy level and leveling pipe at sites.
22.Size
of Concrete cube
150mm x
150mm x 150mm
23. Fe-415 Steel Grade
415
indicates that the Yield strength (Tensile strength when it is sunjected to
elongation) of steel is 415N/mm2
24.
Volume of 50 Kg Bag of Cement
Volume
of 50 Kg bag of cement is 0.035 Cum
25.
Minimum Dia. of steel in Columns
12mm
26.
Maximum Reinforcement in beams
0.04bD
(4% of total gross area)
27.
Minimum reinforcement in slabs
0.12% of
gross area
28.
Minimum reinforcement in beams
Minimum
area of tension reinforcement shall not be less than Ast/bd =0.85fy
Ast
- Min. area, B-breadth, D-Depth of Beam, fy-Charcateristic strength of
reinforcement in N/mm2
29.
Maximum Reinforcement in Columns
Max.
reinforcement ratio will be 0.04 times the Columns's gross area (4%)
30. AAC
Blocks
Autoclaved
Aerated Concrete Blocks
31. Min.
no. of rods provided in Rectangular Columns
4
32. Min.
no. of rods provided in Circular Columns
6
33.Flat
Slab
The Two
way reinforced slab which is supported on Columns (Don't have beams)
34.
Compressive strength of Brick
For
First class bricks - 10.3 N/mm2 (105 Kg/cm2)
35.
Water absorption of First Class Brick
Max. 20%
36.
Different types of slabs
One-way
slabs on Beams, One-way Joist slab (Ribbed slab), Two way slabs on beams,
Waffle slab, Flat slab, Hollow core slab, hardy slab, Bubble deck slab,
Composite slab, Precast slab, Grade slab(on Ground)
37.
Initial and Final setting time of Cement
Initial
setting time is 30 minutes and Final setting time is 10 Hours.
38.
Methods of Curing of concrete?
1.
Sprinkling of water 2.Wet Covering with gunny bags 3. Ponding 4.Steam curing 5
Membrane curing 6.Using curing chemicals
39.
Types of Foundations
Two
types of foundations - Shallow and Deep foundation. Again Shallow foundations
can be classified as Spread Footing, Combine footing, Strap or Cantilever
footing and Mat or Raft footing. Deep Foundations can be classified as Pile
footing, Pier footing, caissons footing and well foundation.
40.
Construction Equipments
1. Earth
moving equipment - Excavators, Backhoe, Loaders, Bulldozers, Graders,
Trenchers, etc.
2.
Construction Vehicles - Dumpers, Tippers, Trailers
3.
Material handling Equipment - Cranes, Conveyors, Forklifts, Hoists, etc.
4.
Construction Equipment - Tunneling and Handling, Concrete Mixers,
5. Road
making machines - Road Rollers, Hot mix Plants, Stone Crushers, Slurry
seal machines, Slurry pumps
41.
Concrete Cover
The
concrete cover in renforced concrete is the least distance between the surface
of embedded steel
reinforcement
and the outer surface of the concrete.
42.
Minimum Covers required
In
footings - 50mm, Columns - 40mm, Beams -25mm and slabs -20mm.
43. TMT
Bars
TMT -
"Thermo Mechanically Treated" Bars. TMT bars are used in
Construction, since they have high strength and corrosion resistance.
44.Steps
involved in Concreting Process
1.
Batching (Process of measuring Cement, Sand and aggregates) 2.Mixing 3.
Transportation, 4. Pumping, 5. Compaction 6. Curing
45.
Formwork
Formwork
is a type of temporary mould in which concrete is poured to cast the required
shape of concrete.
46.
Different types of Form work
1.
Timber Form work, 2.Steel Form work, 3. Aluminium Form work, 4.Plywood Form
work, 5.Plastic Form work and 6. Fabric Form work
47.
Difference between Lap length, Development Length and Anchorage Length
Lap
length is the
length that is provided in excess over the another bar to lap one bar over
another.
Itmainly
depends on steel dia. used in reinforcement, grade of concrete to be used and
zone it is used.
As per
IS 456:2000, For direct Tension, the lap length shall be 2Ld that
is development length or 30d whichever is greater is
considered. (d- diameter of the bar). In Compression, lap length
should not be less than 24D. The straight length of lapping
bar shall not be less than 15d or 20 cm.
Development
Length (Ld) is the length of bar required to transfer load or stress
from steel to concrete.Generally Development length is 41d.
Anchorage
Length is
provided if sufficient development length can not be able to be provided inside
the support/fixed end.
48.
Guniting
It is a
process in which mixture of cement & sand in proportion of 1:3 is shot on
concrete surface with the help of cement gun uder pressure of 2 to 3 kg/cm2. It
is a highly effective process for repairing concrete walls or damaged surfaces.
49.
Grouting
It is
the process of injecting the Grout into cavities or cracks in concrete,
masonry, soil and rocks. Different materials of Grout are
Cement Grouting, Chemicals Grouting, Bentonite Grouting, Resin?Epoxy Grouting
and Bituminous Grouting.
50.
Flashing
Flashing
is an extended construction that is done to seal and protects joints in a
building from water penetration. Flashing is installed at the intersecting
roofs, walls and parapets.
51.
Expansion Joint
In
buildings, an expansion joint is a mid-structure seperation designed to relieve
stress on building materials caused by building movement induced by thermal
expansion and contraction caused by temperature changes, sway caused by wind,
seismic events.
As per
IS 3414, which is specific code for joints, structures exceeding 30m length
are designed with one or more expansion joints.