A COMPLETE GUIDE TO
TOTAL QUALITY MANAGEMENT - I
OBJECTIVES
Our Quality Management System will be implemented to ensure
construction procedures in each definable feature of work are performed in
compliance with the plans and specifications. This TQMS will provide a means to
maintain effective quality control at the project site. The quality control
measures as presented herein include quality control organization, methods of
performing, documenting, and enforcing quality control operations (including
inspection and testing).
INSPECTIONS
A specific Inspection schedules will be followed and in
order to maintain proper records of the inspections different forms will be
used. These inspection stages include;
. Preparatory inspection
. Initial Inspections
. Follow-up Inspections
. Additional Inspections
Stage 1: Preparatory Inspection
Preparatory inspections will be performed prior to beginning
work on any definable feature of the project one week prior to conducting a
Preparatory Inspection. This stage will include:
. Review work requirements, Check to ensure all materials
and equipment are on-hand, have been tested, submitted, and approved, document
the Preparatory Inspection meeting and send copies of the meeting minutes to
all parties.
. Check to assure that provisions have been made to provide
required field quality control testing
. Examine the work area to ascertain that all preliminary
work has been completed
. Verify all field dimensions and advise consultant of any
discrepancies
. Perform a physical examination of materials and equipment
to assure that they conform to approved shop drawings or submittal data and
that all required materials and/or equipment are on hand and comply with the
Contract requirements.
Stage 2: Initial Inspections
Initial stage inspections will be performed as soon as a
representative portion of the particular feature of work has been accomplished.
Initial inspections include, but are not limited to, examination of the quality
of workmanship, review of control testing for compliance with control
requirements.
The initial phase inspection is the time to discuss the
required level of quality associated with a given work activity.
Stage 3: Follow-up Inspections
Follow-up inspections will be performed daily as work
progresses to ensure continuing compliance with contract requirements,
including control testing, until completion of the particular feature of work.
Final follow-up inspections will be conducted and deficiencies corrected prior
to beginning new work.
Stage 4: Additional Inspections
In addition to the above discussed inspections, another
three inspections will be performed before hand over the project. Those are
punch-out inspection, pre-final inspection and final acceptance inspection.
These inspections will ensure that the project has achieved all the final
quality requirements.
Punch-Out Inspection
The punch out inspection checks the last repairs and
corrections of all the systems and components such as beams, roof structure,
frame carpentry, plumbing top out, electrical rough in, HVAC rough in, roof
covering inspection and stucco installation. The inspection with a detailed
list of corrections items and repairs needed prior to closing. These checks
will be conducted by site manager as quality QCM.
Pre-Final Inspection
When the construction has been substantially completed by
the contractor, a pre-final inspection will be held. Those who should attend
this inspection are the project manager, site manager and QA support at this
inspection, following items will be submitted/ completed:
Final Acceptance Inspection
When all construction including punch list items have been
completed in accordance with the approved plans and specifications and the
project is operating as designed, the final inspection can occur. Those who
should attend this inspection are the project manager, representative from
contractor, site manager and QA support at this inspection, following items
will be submitted/ completed:
. Verification of punch-list items have completed.
. All required record drawings, maintenance bonds,
warranties, guaranties, parts catalogs, etc., delivered to Project
Manager
. Lien waivers for all subcontractors and suppliers
presented to contractors
. Contacts for warrantee work by the Project Manager
• Verification that punch-list items are completed.
• A balanced financial status for the project. Include all
expended costs, the final reconciliation of quantities (“clean-up”) change
order, any retain age to be withheld, and catalog any miscellaneous outstanding
project costs.
Inspection Parameter |
Minimum QC Inspection Frequency |
Acceptance Criteria (verified by ) |
Reinforcing Material Condition |
Upon receipt at Site |
No visible defects or damage, no unscheduled kinks or
bends |
Reinforcing Bundle Identification |
Upon receipt at Site |
Bundled and tagged with information |
Reinforcing Material Storage |
Daily |
In accordance with Manufacturer’s recommendations & approved Work Plan |
In-Place Reinforcing |
Prior to closing forms and continuous during pouring |
In accordance with approved Work Plan, free of old mortar,
oils, mill scale and other encrustations or coatings |
In-Place Formwork |
Prior to pouring of concrete |
In accordance with approved Work Plan; no excess water,
hardened concrete, debris or foreign materials inside of forms, wet wood
forms sufficiently to tighten up cracks |
Concrete Truck |
Upon arrival at Site |
Load accompanied by weight master bonded certificate,
water container full, water added to concrete mixture in accordance requirement |
Sub grade Preparation |
Prior to pouring of concrete |
Fine grade earth and aggregate smooth and level |
Concrete Placement |
Continuous during pouring of concrete |
In accordance with approved Work Plan, height of concrete
drop not to exceed 5 feet, place and compact within 60 minutes after water is
first added, do not place after evidence of initial set |
Equipment Size and Type |
Continuous during pouring of concrete |
In accordance with approved Work Plan |
Concrete Lift Thickness |
Continuous during pouring of concrete |
Max. 18 inches per lift in continuous approximately
horizontal layers |
Maximum Deviation |
Continuous during compaction of concrete |
1/4-inch from 10-foot straightedge for exposed finishes,
no low spots to impound water |
Formed Concrete Curing |
Daily during curing of concrete |
Forms maintained in wet condition until removed, concrete
continuously moist for min of 7 days after pouring |
Formed Concrete Finishing |
After finishing of concrete |
Fill holes and patch surfaces in accordance with specification |
Slabs and Flatwork Curing |
Daily during curing of concrete |
Concrete continuously wet for entire curing period |
APPENDIX 3: INSPECTION CHECKLIST
Inspection Checklist
Under the quality inspection following major type should be checked.
Excavation
The following characteristics of excavation should be
reviewed:
1. Perform a thorough review of all site exploratory reports
made during design and during construction.
2. Preview site plans to note any underground structures to
be avoided, such as pipes and utilities.
3. Prior to commencing excavation, clearing, grubbing and
stripping operations should be completed to the areas shown on the site
excavation drawings. Provisions should be provided for dust abatement.
4. For mass excavation remove soil, boulders, coal and any
other unclassified materials to the lines and grades shown on the
drawings.
5. For structural excavation remove in-situ materials for
structures, underground utilities, pipes, culverts, drains or diversion channels
to the lines, grades, elevations and dimensions shown on the drawings.
6. Sumps and well points should be constructed and adequate
pumps should be provided to prevent groundwater accumulation in the excavation.
7. Random sampling and testing should be performed on
excavated material to note changes in soil classification or physical
properties.
8. Borrow areas should be properly maintained to provide
effective drainage and erosion control.
9. Excavation should be made to the lines, grades, elevations
and dimensions as shown on the drawings or as directed by the foundation
engineer or geologist to obtain a suitable foundation.
10. Completed excavation should be inspected, tested and
accepted prior to placement of mud mats, slabs, pipes or structural backfill.
QUALITY CONTROL PLAN
Earthwork (backfill)
The following characteristics of earthwork should be
reviewed:
1. Determine the material requirements for the different
types of earthwork on the construction project.
2. Check that material sources have been approved.
3. If method specifications are used, determine the
compaction requirements. Determine what degree of compaction is needed to
satisfy design criteria. Determine the type and weight of compaction equipment
required and the number of equipment passes at a specified lift thickness
necessary to meet density requirements.
4. Check that provisions are adequate for dust
abatement.
5. Foundation should be inspected, tested and accepted prior
to start of fill operations.
6. Provisions should be adequate for control and disposal of
surface and subsurface water.
7. Fill and borrow areas should be maintained to provide
effective drainage and are protected against erosion.
8. Field and laboratory tests should be conducted at the
frequency specified to verify physical requirements of the fill material.
9. Fill material should meet moisture, compaction and
density requirements and be placed in the specified lift thickness.
10. Moisture and density tests should be performed at random
locations and at specified frequency.
11. Fill material should be brought to final grade and
inspected tested and if acceptable then accept.
Concrete placement
The following characteristics of concrete placement should
be reviewed:
1. Placing equipment is clean and free of loose concrete,
mud, and other debris that could jeopardize the quality of the structure.
2. Reinforcing steel and embeds are clean and free of loose
rust, grease or other matter that may adversely affect concrete bond.
3. Embedded piping has been tested as specified.
4. Joints and surfaces to receive concrete are free of
deleterious materials.
5. Forms are clean and free of foreign material.
6. Provisions for hot or cold weather concrete protection
are provided.
7. Concrete is placed in a manner to prevent
segregation.
8. Placement of concrete is made in lift thickness as
specified and within time restrictions between lifts for high lift
placements.
9. Concrete is properly vibrated.
10. Placement is made to avoid excessive drying of fresh concrete
before next lift is placed.
11. Concrete is sampled and tested at specified frequency
for strength, slump, and temperature and unit weight.
12. Concrete is brought to final grade and finished as
specified
Appendix 4.2: Field Inspection Check List for Earth Work
I
Field Inspection Checklist Earthwork |
Job Number |
Project |
|||
CONTRACTOR:
__________________________________ CONTRACT
NO: ___________________ REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):____________________________________________ |
|||||
ATTRIBUTE |
YES |
NO |
N/A |
||
GENERAL Is area released for work? Is equipment adequate? Are existing structures and utilities adequately
protected? Is removed material properly dispositional? Dust and dirt control: a) Haul routes maintained for dust control – by water or
chemicals? b) All paved areas kept clean? EXCAVATION OF TRENCHING Does completed depth and configuration comply with
drawings and Required shoring and bracing in place? Existing utilities protected? PLACING AND COMPACTING FILL Excavation properly compacted and verified by test lab? a) All sleeves, pipe cable, grounding, conduit installed
and approved? b) Approved fill material is used? Is fill being placed in level lifts within thickness
limits? Is proper compaction attained and verified by test lab? Have contaminated (and spongy) areas been cut out, filled
and compacted with approved material? |
|
|
|
||
Appendix 4.3: Daily Concrete Inspection Report
Daily Concrete Inspection Report
Job Number Project Page of 1/1
CONTRACTOR:
-----------------------------------------------------------------------------------------------------------------------
SPECIFIC LOCATION
AREA/BUILDING-----------------------------------------------------------------------------------------
STATION: -------------------------TO
STATION: ------------------------- OFFSET:
--------------------------------
T/OFFS: ------------------------------ ELEVATION:
------------------------- TO ELEV: -----------------------------CONCRETE
TYPE: ---------------- MIX NO:
----------------------ADDITIVES: --------------------------
TYPE OF DELIVERY:
----------------------------------------------------------------------------------------------------------------
DELIVERY EQUIPMENT IDENTIFICATION/NUMBER: --------------------------------------------------------------------
PLACEMENT STARTED: DATE -----------------------
TIME------------------SHIFT------------------
PLACEMENT COMPLETED:
DATE----------------------TIME------------------
SHIFT------------------
WEATHER CONDITIONS:
-----------------------------------------------------------------------------------------------------------
TOTAL CONCRETE PLACED:
------------------------------------------------------------CONCRETE WASTED:
-------------------------
REASON: --------------------------------------------------
AVERAGE SLUMP: --------------- TEMPERATURE:
------------------ % AIR CONTENT: ----------------
TEST CYLINDERS PREPARED:
---------------------------------------------------------------------------------------------------
TRUCK IDENT: ------------------- TOTAL CYLINDERS:
------------ CYL IDENT: ----------------------SURFACE
CONDITION PRIOR TO PLACING:
---------------------------------------------------------------------------------
MAXIMUM FREE FALL OF CONCRETE: ------------ PROPER
CONSOLIDATION: ---------------------------
AMOUNT VIBRATORS: ----------------------------------
VIBRATORS IDENT/RPM: -------------------------------
REINFORCING DISTURBED/REPLACED/REPAIRED:
--------------------------------------------------------------------TYPE
FINISH SPECIFIED:
---------------------------------------------------------------------------------------------------------
FINISHING STARTED: DATE-----------------------
TIME--------------SHIFT-------------
FINISHING COMPLETED: DATE----------------------- TIME
------------- SHIFT --------------
CONDITION OF FINISH:
-------------------------------------------------------------------------------------------------------------
DELAYS (INDICATE TYPE AND REASON: PERSONNEL, EQUIPMENT OR
PLANNING):-------------------------
---------------------------------------------------------------------------------------------------------------------------------------------
OBSERVATIONS/REMARKS:
-------------------------------------------------------------------------------------------------------
CONCRETE INSPECTOR:
------------------------------------DATE:
---------------------------------------------------------