USEFUL GUIDE FOR
CONCRETING
METHODOLOGY
1. INGRADIENTS FOR CONCRETE
a) CEMENT
- Use
appropriate grade of cement as recommended by the consultant and
confirming to IS 456:2000.
- Manufacturers
test certificate should accompany each consignment and cement should be
consumed within 1 month of their manufacturing date.
- Cement
should be stored properly in stacks not more than 10 bags, clear from the
walls by 1 metre and protected at all time from moisture. However, do not
wrap the bag with polythene sheets, sweating may occur.
- Identify
each lot/ consignment of cement and follow a first in first out (FIFO)
method of issue of bags
- Each
consignment of cement should be tested in-house for consistency, setting
time, and strength
b) AGGREGATE
- For
RCC works coarse aggregates confirming to IS 383 and IS 2386 having
maximum size of 20mm and down.
- It
should be obtained from crushed granite, trap, and basalt quarry. It
should be chemically inert, rounded or angular in shape and free from
dust, foreign matter and not thin porous, laminated or flaky.
- Fine
aggregate shall be gritty sand with FM range between 2.6 to 3.2, silt
content should not be more than 5% and there should be no traces of salt.
Aggregate with specific gravity less than 2.6 should not be used.
- If
dirty, wash sand before use. Sand should be clear of organic material
c) WATER
- Water
should be clean, fresh and free from oil, acid, alkali and organic matter
- Potable
water is considered good for concreting and curing
- IS
456:2000 gives permissible limits of solids
d) ADMIXTURES
- Use
of admixture/ additive should be done only after obtaining technical
clearances from technical consultant
- Dosage,
point of application, the desired results should be clearly understood
- Accelerators,
retarders, plasticizers, integral-waterproofing compound are the additives
commonly used
- Expiry
date of the chemical should be checked before use
2. MIXING OF CONCRETE
a) IN-SITU MIXING
- Ensure
adequate stock of all ingredients of concrete i.e., cement, aggregate,
water and any admixture if used for the day’s work
- Use
calibrated Farma (calibration done once in a month) for measurement or in
case of weigh batching, use a weigh batcher machine
- Charge
the rotating drum with 25% of required water to rotate 3-4 times

- Generally
20 to 25 litres is recommended for 1 bag of cement. The water cement ratio
is kept 0.4 to 0.5. The moisture content of aggregates has to be checked
at frequent intervals
- Load
the hopper with ½ the coarse aggregate followed by ½ the fine aggregate.
Above this the entire quantity of cement should be spread. Then half the
quantity of fine aggregate followed by balanced coarse aggregate should be
loaded. This type of sandwiching is done to avoid spilling of cement while
discharging into the drum. Immediately after loading the drum balance
quantity of water is added
- The
drum should be rotated for at least 1 ½ to 2 minutes. The rotation of the
drum is about 15 to 20 revolutions per minute.
- If
plasticizer is used, one litre of water should be held back. Add requisite
quantity of plasticizer to the water and mix it thoroughly. This mixture
is poured into the drum after the drum has rotated for about one minute.
The drum should be rotated for at least 1 minute after adding the
plasticizer mixture to ensure proper dispersion.
Minimum cement content per Cum of concrete is as given
below:
Grade
|
Characteristic strength after 7 days (N/mm2)
|
Characteristic strength after 28 days (N/mm2)
|
Minimum cement content per Cum
|
M10
|
7
|
10
|
220 kgs
|
M 15
|
10
|
15
|
280 kgs
|
M 20
|
13.5
|
20
|
320 kgs
|
M 25
|
17
|
25
|
360 kgs
|
M 30
|
20
|
30
|
390 kgs
|
- No
grade below M 20 shall be used for RCC works.
- Concrete
should be placed in position and compacted within half an hour of mixing
of the same
- Always
keep a supervisor on the mixer to monitor the works.
- Use
large bandlies, wheelbarrows, hoist machine to expedite transporting
process. Wet the surface of the carrier to avoid moisture loss due to
adsorption
- Be
careful to avoid segregation and wastage during transportation. In case of
segregation, remix the concrete before placing.
- Concrete
by vision should be homogeneous in colour, well graded, fluffy and it
should form a shape of ball when rounded in the hands.
b) BATCHING PLANT MIX (RMC)
- Preference
for ready-mix concrete from reputed companies possessing automated
batching
plant, of at least 30 cum per hour capacity supported by
adequate number of transit mixers.
- The
logistics should be worked out so as to receive at least 1 load of 6 cum
every 10 to 15 minutes
- Check
the empty transit mixer for preset concrete in the drum. Preset quantity
affects the quantum of concrete received
- Concrete
should be received with a delivery challan and data cycle sheet showing
grade, quantity, water cement ratio, slump, cement content, time of
manufacturing, dosage of additive added, weight of various ingredients of
concrete.
- Go
through the cycle data before accepting the concrete
- Do
not accept concrete after 3 hours of mixing
- Do
not recharge the concrete by adding additive, water, cement without prior
permission for the project in-charge
- Slump
recommended for RMC mix is 100mm to 125mm
- Place
the concrete pump on horizontal, hard even surface and keep the approach
area free of materials to facilitate easy maneuverability of transit
mixers. The approach should not slope towards the concrete pump.
- The
horizontal section of pipe should be at least 7 metres before the vertical
bend is put.
- Reduce
the length of pipe to the minimum to reduce frictional losses and
excessive strain on the pump.
- The
pipeline should be independently supported on vertical segment and not on
the shuttering. The vibrations due to pumping should not affect or
displace shuttering works.
- Pump
rich slurry (one bag) before pumping concrete to lubricate the inner
surface of the pipes.
- In
case of intermittent supply keep the current transit mixer unloading in
progress until the next mixer arrives at site. This avoids choking of
pipeline due to non-pumping for long duration. Avoid reverse stroke to
clear a choke. The fluid gets flushed out and the problem gets compounded.
- Do
not bend the flexible end pipe by more than 1350 while concreting.
- In
constricted areas do not unload directly from the pipe. Use bandly and
mumty to shift and place concrete in such areas.
- Be
excessively careful while passing the ball while clearing the concrete in
the pipeline after the day’s work is over. Due to negligence somebody
could get hurt.
- Employ
professional hands for connecting pipeline. They will do a neater and
faster job without any safety problems
- Leave
the pipeline, under the pump and adjacent areas clean of concrete dumping
after the work is completed
3. PLACING AND COMPACTION
- Do
not use chutes longer than 4.5m or inclined at more than 45 to horizontal
to pour concrete.
- Place
cement concrete to the required depth and vibrate it until entrapped air
inside concrete is released.
- Pour
concrete first into beams and then over the slab portion.
- BOND
NEW CONCRETE TO PREVIOUSLY POURED CONCRETE
- If
the previous pour was less than 4 hours prior, the laitance film and
porous layer shall be removed from surface of previous pour.
- If
the previous pour was more than 4 hours prior but less than 30 days old
observe the above process and expose aggregate with wire mesh and wash
with clean water.
- If
the joint is more than a month old use bonding agents as per specification
of the manufacturer.
- If
the beam is more than 500mm deep, concrete it in layers.
- Columns,
beam, slab level of concrete top should be pre-marked before start of
concreting works.
- Check
the slab level during concreting with line dori method and also the
leveling instrument.
- Use
appropriate needles for vibration depending on the aggregate size,
reinforcement spacing and element to concrete. For big footings use 60mm
needle, for slabs use 40mm needle, and for starters and precast lintels
use 25mm needle. Vibrators should operate for a speed not less than 10,000
rpm. Ensure that just adequate vibration is only done. Over vibration is
very bad.
- Use
wooden runner to ram so as to form slurry on top of the concrete surface.
- Clean
the shuttering works of all spilled concrete immediately after concreting.
- Leave
vertical construction joints after consultation with the structural
engineer.
- Match
the vibrators, masons to the rate of concreting.
- All
surfaces of shuttering shall be moistened before placing of concrete to
reduce water loss due to absorption.
- Slab
should be sprayed with water after covering with hessain cloth 3 hours
after concreting, i.e. initial setting is over and ensure that hessain
cloth will remain wet till ponding of water.
- Pond
water to a depth of 25mm using bunds the next day and keep water standing
for 7 days at a stretch.
- In
case ponding is not possible, cover it with hessain cloth and keep it
moist throughout.
- DO
NOT IGNORE CURING OF SLAB TO FACILITATE MARKING OF COLUMNS FOR THE UPPER
SLAB.
- The
beam bottoms should be cleaned using high-pressure cleaners.
4. COLUMNS, WALLS AND STARTER
- Remove
the shuttering the next day and wrap with moist hessain cloth after
spraying the column with water to reduce the heat of hydration
- The
columns and walls should be cured for a minimum of 7 days.
- Starters
are to be cured for 3 days.
5. TESTING OF CONCRETE
a) Slump Test
- Conduct
slump cone test, one during the start, one at midday and one towards the
close of days work.
- Again
any load under suspect can be checked for slump on case-to-case basis.
b) Cube test
- The
sample is made at point of discharge of mixture.
- Take
3 samples after 7 days and 3 samples after 28 days strength.
- Every
100 cum or 10 batches of concrete (whichever is smaller) should be
represented by a sample of test cubes.
- For
concrete manufactured at site, there must be representative samples for
the day’s work and for different elements like footing, slab, column and
wall.
- Test
results should be discussed with the project in-charge even if the results
are satisfactory
- In
case of cube failure, the element to be identified and non-destructive
test to be conducted. Cube results of the RMC supplier for the same batch may
be checked.
TOOLS REQUIRED FOR CONCRETING
The following tools must be available at site to ensure
correct work.
1. Trowels
2. Shovels
3. Line dori
4. Gum boots
5. Vibrator
6. Dumpy
levels
7. Spirit
levels 1-3m
8. Measuring
tape
9. Masons
trowels
10. Floating
trowels
11. Screed
finishing darby
12. Steel trash
tracks
13. Hammer
14. Leveling
trowels
15. Wheelbarrow
16. Long handle
Aluminium leveler
17. Masons
brushes and buckets
18. High
pressure water cleaners
INSPECTION METHODOLOGY FOR QUALITY ASSURANCE
1. Personnel
- Ensure
all personnel are wearing gumboots and rubber gloves
- Ensure
personnel at wearing safety belts during concreting at heights or on
periphery of structures
2. Before
Concreting
- Ensure
base plate have been cleaned and sealed with sealing tape so as there is
no leakage of slurry
- All
reinforcements are in place especially chairs
- All
cover blocks damaged during reinforcement layout are replaced
- All
sunken areas (sunken beams, toilets and cutout areas) have been properly
cleaned of dust and oily substances using high-pressure water cleaners
3. During Concreting
- Ensure
proper grade of concrete as recommended by the consultant is employed
- Ensure
proper expansion joints as per working drawings and protected
- Check
slab and beam for parallelity using spirit levels before and after
concreting
- Check
the top surface of fresh concrete for eveness of top surface
- Ensure
sufficient compaction using correct needle size of vibrator
4. After Concreting
- Curing
carried as per guidelines
- Columns
are covered with a damp hessain/ jute cloth for 7 days
- Slabs
– water level is maintained during ponding
- If
honeycombing seen after de-shuttering, immediate touch up without delay
- Ensure
the cube test results are available at the end of the term indicated