WATERPROOFING IN
BUILDINGS - METHODOLOGY
WATER PROOFING FOR FLAT ROOFS AND SLOPED ROOFS
1. The
surface to be waterproofed should be prepared thoroughly by chipping all cement
mortar deposits/ loose material, dust etc. using a chisel, wire and coir brush.
2. The
surface, which is to be waterproofed, should be ponded with water and any
dampness / leakage should be marked in the ceiling below the terrace. Wherever
leakage persists, 12mm diameter GI nipples should be fixed depending on the
depth of dampness, on such weak locations in the ceiling and it is pressure
grouted with neat cement slurry admixed with expansive grouting.
3. ‘V’
grooves should be cut along the concrete / brickwork junctions on joints.
Surface cracks if any should be filled with polymer modified diluted solution
and also in cutouts, around the sleeves, drain pipe joints and filled with
sealant.
4. Every
upturns and pipe outlets should be reinforced with fiber mat between the two
coats
5. Two coats
of Acrylic polymer based waterproofing system or equivalent should be applied
on terrace and parapet walls. One coat of neat cement mixed with polymer
additive should be applied as bonding coat.
6. A
protective screed of 20-25mm thick should be provided with proper slopes. The
treated area should be plastered to required slope as per drawing and cured for
a minimum of 3-4 days.
7. To ensure
water tightness, the treated area shall be filled with water and tested.
8. Over the
treated surface, weathering course tiles should be laid on the terrace maintaining
a proper slope.
WATER PROOFING FOR SUNKEN AREAS/ SLABS
1. The
surface, which is to be waterproofed, should be cleaned thoroughly from all
loose material, and dust, using wire and coir brush.
2. The
surface, which is to be waterproofed, should be ponded with water and any
dampness/ leakage should be marked in the ceiling below the terrace. Whenever
leakage persists, 12mm diameter GI nipples should be fixed depending on the
depth of dampness, on such weak locations in the ceiling and it is pressure grouted
with neat cement slurry admixed with expansive grouting.
3. ‘V’
grooves should be cut along the concrete / brickwork junctions on joints.
Surface cracks if any should be filled with polymer modified diluted solution
and also in cutouts, around the sleeves, drain pipe joints and should be filled
with sealant
4. Two coats
of Acrylic polymer based waterproofing system should be applied as a bonding
coat on the treated surface.
5. All
joints between the beam and blockwork should be covered with the fiber mat.
6. Plaster
the treated area with neat cement and high grade waterproofing additive to the
required slope as per drawing to protect the coating from wear and tear.
7. The
treated area should be subjected for testing by ponding water at least for a
depth of 150mm for 24hrs.
8. The
chasing for concealed plumbing, and electrical works should be completed before
the start of waterproofing and the chasing must be treated with an agent such
as FORMDEX.
9. Over the
treated area, stone dust should be filled and roughly finished with 75mm thick
screed concrete 1:2:4 to facilitate laying of tiles. The screed concrete floor
level should be 20mm below the main floor, to facilitate a level difference
between main area and toilet after tiling and to prevent toilet water entering
the main area.
METHODOLOGY OF WATERPROOFING IN TOILET AND SHOWER/ WASH
AREAS USING MUREXIN COMPOUND
1. Ensure
the cement plastering for all toilet and shower areas are plumb, and at right
angles to the facing walls, ceiling and floor levels. Further the plaster
should have an even surface and a slightly rough texture. The flooring during
the finishing stage must be adjusted to the slope of screed level set towards
water-outlets.
2. After
sufficient time for setting of plaster, clean the plastered surface using a
mason’s brush of all dirt and dust particles. Before each application, the base
must be dry and free of all dust-particles and foreign materials.
3. Mark out
the areas to be waterproofed, with the help of a pencil, measuring tape and
spirit levels. Separate this area from the rest using masking
tape.
4. Apply the
base coat MUREXIN LF as the first coat. This coat is done uniformly using the
Masons brush over the entire area. Allow this coat to dry for about 20 minutes.
Let the drying process be natural and do not subject the area to any
wind-draft.
5. During
the drying period of the base-coat, the two component sealing material MUREXIN, made
up of the powder component and the liquid component should be mixed slowly and
evenly in the ratio of 2:1, using the mechanical stirrer (imported from Germany
for the purpose). For example, for every 2 Kg of Powder component mix
with 1 Litre of the liquid compound. Stir this mixture slowly and uniformly in
to a homogenous mass free of any knots or nodules (Mixing time- 3
minutes).
6. Now the
well-mixed sealing medium maybe applied uniformly using the 6mm teethed trowels
first vertically in all the corners, in the spray areas of the shower area up
to a height of 2 meters and in the rest of the toilet area to a height of 0.30
meters. Subsequently the MUREXIN sealing strip (caulking strip) will be placed
along the corners and fixed uniformly using the right edged trowel and pressed
firmly along the corners. Now please ensure that the sealing strip –also
called the caulking strip, is fixed firmly in the corner ensuring there is no
air gap.
7. Subsequently
the sealing compound is applied uniformly using the 6 mm-teethed trowel
ensuring the thickness of the applied layer is maintained evenly at 1 mm. In
the region where the pipe connections project from the plastered area, overlap
such areas with the strips and apply the compound to fix them. After
sufficient time for drying (About 24 hours), the second layer of 1 mm layer is
to be applied thus bringing the total thickness of the application to 2 mm. Now
remove the masking tape.
8. After
allowing about 24 hours for drying, the walls are tiled, using
“MUREXIN-Flexi-mortar” adhesive using the 6 mm teeth trowels.
9. After the
walls are completely tiled, the flooring tiling is also taken up in a similar
fashion. This means repetition of the procedures 1 to 8 before the floor
tiles are brought on, so that the flooring is also well water proofed and
sealed.
TOOLS TO BE USED BY TRADESMEN
Required tools must be available at site to ensure correct
work. Basic tools of the waterproofing gang are:
1. Dumpy
levels
2. Line dori
3. Spirit
level
4. Tube
level
5. Plumb bob
6. Aluminium
straight edge
7. Trowels
8. Mason’s
brush
9. Mechanical
Stirrer (German)
10. 6mm teethed
trowel
11. Right edged
trowel
12. Finishing
boards and sponge
13. Chipping
tools
14. Hammer
15. Water
barrel
16. Bitumen
roller
INSPECTION METHODOLOGY FOR QUALITY ASSURANCE
1. Check
method of waterproofing is as per recommended by consultant and proper
application methods
2. Check for
all the drawings with relevant details for water proofing treatment is
available with the site staff
3. The
detailed instructions of waterproofing should bear the signature of the
consultant
4. PVC water
stoppers must be ensured at the junction of all joints in the water retaining
structures like tanks, swimming pools etc.
5. The
waterproofing supervision job card should be attached.