FORM
WORKS - METHODOLOGY
Ø Formwork
is temporary support given to concrete until it gains strength to withstand its
self-weight.
Ø Formwork
shall be so designed to support safely the worst combined effects of all loads
within acceptable dimensional tolerance and without causing bulging or
deflection. Formwork should be:
Ø It
should be dimensionally accurate and give the desired finish to the contact
surface.
Ø Always
use staging of MS tubes with timber runners. The staging should be placed on
hard even surface. If placed on ground compact it and use planks under the base
plate to distribute load. Base plates should not be placed on concrete blocks
or bricks, which are likely to get crushed when wet.
Ø Staging
shall be true, rigid and thoroughly braced, shuttered and propped.
Ø To
achieve desired rigidity ample studs, braces, bolts, spacer blocks and stay
wire to be given to avoid distortion.
Ø Check
the shuttering work for vertical and horizontal alignment, level, surface
cleanliness, water tightness, and ability to withstand loads without
distortion.
Ø Scaffolding:
At the ground level, walk round the perimeter of the scaffold and check
for
Rectify with adjustable
base plates or fill with concrete
Do not use Casarino poles/
Bamboo as struts or supports.
Ø Guardrails
and toe boards
Both guardrails and toe
boards should be fixed to the inside of the outer standards and remain in
position before decking is removed. Guardrails should be fitted at not less
than 0.9m and not more than 1.15m above the decking. Toe boards should be at
least 150m high above the decking and the clear spacing between the guardrails
and the boards should not exceed 0.75m.
Ø Formwork
oil
Ø All
spans in excess of 5 metres for beams and slabs should be kept within a pre
camber of 2mm per 1 metre. For cantilever, give a camber at the end of span of
4mm per 1 metre.
Ø The
quality of finished concrete is dependent on the quality of formwork.
Ø Erection
casing and shifting of formwork shall be done under the personnel supervision
of a competent foreman.
Ø Striking
time for formwork is as follows under normal conditions.
Walls, Columns, Starters
etc – 24 hours
Slab (span<6mts) – 7
days
Beam (span < 6mts) – 14
days
Slab beam (span > 6mts)
– 21 days
Props to cantilever – 28
days
Ø For
balcony and other rib beams, duct beams support should be continuous for at
least 3 floors.
Ø Due to
weather conditions if the concrete is not sufficiently hardened, the striking
time to be extended after discussing with the project in charge.
Ø Obtain
the 7th day cube test result before the removal of formwork.
INSPECTION METHODOLOGY
FOR QUALITY ASSURANCE